Life-study of the Bible
Listen to Life-study of the Bible with Witness Lee
Old Testament
The First Fall of Man
from Life-study of the Bible (Genesis 3:1-13)
6.30am Mon-Sat (Premier Gospel)
New Testament
A Man of God
from Life-study of the Bible (1 Timothy 6:11-21)
8pm Mon-Fri (Premier Christian)
Old Testament Highlights
Catch up?
The next broadcast will be on Lord's Day 8 December
from Life-study of the Bible (Genesis)
6.30am Lord's Day (Premier Gospel)
New Testament Highlights
Catch up?
The next broadcast will be on Lord's Day 8 December
from Life-study of the Bible (1 Timothy)
3pm Lord's Day (Premier Christian)

Life-study of the Bible is a 30-minute radio broadcast which focuses on the enjoyment of the divine life as revealed in the Scriptures.

Woodland Camp Update – 10 August 2019

There was steady progress on site these two weeks. 


The work has focused on the preparation of a second set of five new cabins (for a total of ten new cabins currently under construction). The brothers prepared by setting out the site for the screw piles, boring the holes, installing the screw piles, trenching for the sewage pipes, installing the steel ring beams, and curing the concrete on each screw pile.

After setting out the site the brothers continued to bore holes where the screw piles will be placed.


Using GPS location device, we are able to locate the centre hole and place a rebar. This will help the brothers to know where they should place the screw pile.


The screw piles were installed.


The brothers then trenched the cabins for the sewage pipe and services after all the screw piles were installed.


The trenches were backfilled. 


A ring beam was installed in all of the new cabins. 


The steel beams need to be drilled and fitted on top of the plate of the screw piles.


After the steel beams were installed, the brothers poured concrete into the screw pile holes.


The work continued on the first set of five new cabins.

The brothers continued with the installation of all the metal framing.


Plywood sheathing was installed on the exterior of the cabins.

Decking is beginning to be built.  

Tyvek membrane has been applied to the roofs of the cabins.


Scaffolding has been erected around the first five new cabins, which will allow us to continue the work steadily.