31 January 2020

Posted on January 31, 2020 in Building Project, 2020 Updates

Previous Update

Woodland Camp Archives

Next Update

Woodland Camp Update
31 January 2020  

 

Praise the Lord for another new year and a new beginning for all of us labouring on Woodland camp. This winter, eleven of the FTTL trainees have joined the work during their winter recess, and this has resulted in a great blessing for the progress of the work. The structural steel frames have been installed for the B cabin and the two F cabins. On the rest of the cabins the brothers have finished the internal walls, as well as the plumbing inside all the cabins. The cladding in all the new cabins with the decking has begun. The drywall installation is finished along with the plastering of the walls and the ceilings inside. The shower trays are being installed, as well as the conduit for the HRMV (Heat recovery mechanical ventilation), and the radiators have been tested on the cabins. All cabins have the electrical cables fitted, and the brothers continued to install the lights and the window flashing.

(Scroll through the slideshow below to see this month's progress) 

1 / 36
The fellowship and the one accord have been essential for the progress of the work.
2 / 36
Laying of the sewage pipes for the F cabin services
3 / 36
Data and other services being laid
4 / 36
F cabin steel ring and preparation for the structural steel.
5 / 36
Holes being drilled for steel frame installation
6 / 36
Transportation of the steel frames prior to installation
7 / 36
F cabins structural steel erected
8 / 36
B cabin steel ring and structural steel preparation
9 / 36
B cabin structural steel erected
10 / 36
Finishing the partition walls with electrical cables
11 / 36
Piping and connecting all the fittings for hot water
12 / 36
Leveling of the porch ceiling for the cladding
13 / 36
Insect mesh installed before the cladding on the porch
14 / 36
Cladding on the porch ceiling
15 / 36
Exterior cladding
16 / 36
Central cabins
17 / 36
Cladding on the east side cabins
18 / 36
Decking on a cabin porch
19 / 36
Plastering the walls on the cabins
20 / 36
Shower and toilet floor tiling
21 / 36
Shower trays
22 / 36
The Heat Recovery Mechanical Ventilation unit (HRMV) being prepared for installation
23 / 36
HRMV conduit installation
24 / 36
Trainee installing door frames inside the cabins.
25 / 36
Applying PVA Adhesive to help seal the plaster and waterproof it
26 / 36
Connecting services for the new B and F cabins
27 / 36
Trainees cleaning the refurbished cabins
28 / 36
C10 cabin
29 / 36
Trainees sanding and painting wood details for the cabins
30 / 36
After sanding and painting, being allowed to dry before installation.
31 / 36
Trainees helping out to clean the site
32 / 36
Preparation of the doors for the showers and toilets
33 / 36
The property at Priors had a new sewage pipe installed by the brothers.
34 / 36
The property at Priors had a new sewage pipe installed by the brothers.
35 / 36
The property at Priors had a new sewage pipe installed by the brothers.
36 / 36
Plant room controls are being installed, and site wide underground heating loop is being tested.
#shadow-root(closed)
#shadow-root(closed)


HOW TO DONATE



Resources
Newsletter
Free Study Bible
Daily Radio Broadcast
Updates & News
Reports
Building Project
Woodland Camp
Donations
Contact Us

Amana Trust
Bower House
Orange Tree Hill
Romford, RM4 1PB

110 Pentonville Road
Islington
London, N1 9JB


+44 (0) 1708 380 301
[email protected]

All verses and footnotes taken from the Holy Bible Recovery Version. Anaheim: Living Stream Ministry, 2003.


Copyright © 2018-. All Rights Reserved. Amana Trust, Bower House, Orange Tree Hill, Romford, Essex, RM4 1PB. Email: [email protected]. Registered in England and Wales, company number: 4366897. A charitable company limited by guarantee, charity number: 1093401. VAT: GB711295848 | Privacy Policy

Powered by Configio a Momentive Software owned company