UK Building Project Timeline

Full-Time Training Centre Building Project TIMELINE

2025

March

In the second week of March, our demolishing contractor came to remove all the carpets from the former classrooms.

On the roof of the former classrooms, there were some asbestos areas, and the contractor removed them in a careful way.

In the third week of March, our demolition contractor started to remove the walls of the former classrooms.

In the third week of March, our demolition contractor started to remove the walls of the former classrooms.

In the last week of March, the walls of the large classroom were removed.

In the same week, the contractor started to remove the walls of the small classroom, which had served as the storage location for ministry books as well as the Bibles for Europe (BfE) UK distribution centre.

April

By the beginning of April, all the former classrooms have been demolished.

In the following weeks, we were preparing the site for the retaining wall piling mat.

May

In May, the new electrical transformer with a kiosk had been installed.

From the middle of May to the middle of June, brothers were building the new electrical room for the power supply to the whole Bower House estate.

The new electrical room is next to the kiosk.

June

In the middle of June, we had the specialist piling contractors team come over to build guide walls for the retaining wall piles, the guide wall ensures that each pile is accurately positioned.

After one week, another piling contractor team came to install the contiguous piles. These piles are made of reinforced concrete and are designed to provide lateral support and stability for structures.

July

In July, our brothers were working on installing the capping beams with rebars next to the guide walls and contiguous piles.

Capping beams join pile foundations together to increase their rigidity and reduce movement.

August

In August, the first capping beam pour has been carried out. There were two saints coming from the United States to help for two weeks.

In the middle of August, our brothers were continuing to work on the capping beams, and the second concrete pour took place.

On the last day of August, we started mass excavation after completing the third concrete pour for capping beams.

Brothers were removing large quantities of earth from the construction site to Bower Farm to create a level surface and the desired depth for the further foundation work.

After mass excavation, the retaining wall piles installed in June could now be seen

September

At the end of September, brothers were putting the white filter fabric on the surface of the soil and preparing the crushed concrete work platform.

Directional drilling of ground water drain from excavation out through the hillside

Lower Ground Floor piling

October

Installing concrete form work.

December

Installing heave protection around lift pit slab.

Installing heave protection.

2026

January

Continuing preparation of the classroom (lower ground) floor slab including the reinforcing steel.

February

Pouring of concrete for the first section of ground floor

Pouring of concrete for the second section of ground floor

March

Completing the classroom (lower ground) floor slab heave protection formwork and reinforcing steel for early April pour.

April

During the first week of April the reinforcing steel for the remaining lower ground floor concrete slab was completed.

Completing the lower ground floor slab with visiting brothers perfecting the local saints



Resources
Newsletter
Free Study Bible
Daily Broadcast
Updates & News
Reports
New Training Centre Building Project
Woodland Camp
Donations
Contact Us

Amana Trust
Bower House
Orange Tree Hill
Romford, RM4 1PB

110 Pentonville Road
Islington
London, N1 9JB


+44 (0) 1708 380 301
[email protected]

All verses and footnotes taken from the Holy Bible Recovery Version. Anaheim: Living Stream Ministry, 2003.


Copyright © 2018-. All Rights Reserved. Amana Trust, Bower House, Orange Tree Hill, Romford, Essex, RM4 1PB. Email: [email protected]. Registered in England and Wales, company number: 4366897. A charitable company limited by guarantee, charity number: 1093401. VAT: GB711295848 | Privacy Policy | Terms & Conditions

Powered by Configio a Momentive Software owned company